Desher Kaj
Benches and lighting
Benches and solar lights at a ghat, bus stand or park.
Area
Barishal
People
5 people
Time
About 20 hours
Difficulty
Medium
About this task
Lasting benches built by a local mason at a ghat, bus stand or park, and solar lights for the night, with the authority’s permission and one local person to look after them.
Why it matters
Old people, patients and fathers with babies wait for hours on their feet. Dark places are unsafe at night. A seat and a light make a place everyone’s.
What changes after
Benches in use, lights on at night, and one named person with a number looking after them.
Who can join
Anyone; a mason or electrician on the team keeps the cost down.
Step by step
- 1Done
Spot and permission120 min
Where people wait the longest; permission from the owner of the place.
- 2Done
Mason and purchase300 min
A quote from a local mason; buy with receipts.
- 3Done
Install480 min
Benches set in concrete, lights on a pole facing the seats.
Checklist to get ready
- Solar lights · ৪টি
When it counts as done
- Benches in use, lights on at night
Proof required: Before photo, After photo, Receipt
⚠ Safety
Solar lights fitted by someone who knows the wiring. Cement work with gloves.
What it costs
| Cement (50 kg bags) | 6 bags | ৳520–600 |
| Sand | 20 cft | ৳30–60 |
| Stone chips or brick chips | 10 cft | ৳120–180 |
| Steel rod | 30 kg | ৳90–110 |
| Mason and helper wage | 3 days | ৳1,500–2,200 |
| All-in-one solar light | 4 | ৳1,500–4,000 |
| GI pipe poles (10–12 ft) | 4 | ৳800–1,500 |
| Bolts, clamps and paint | 1 lot | ৳500–1,000 |
| Total (about) | ৳21,800–39,500 | |
Getting ready, step by step
3–4 weeks before
See where people wait longest on their feet; take photos.
Apply in writing to the owner of the place.
Get quotes from two masons.
7 days before
Make sure the written permission is in hand.
Buy materials and keep every receipt.
Get a neighbouring shopkeeper or ghat worker to agree to look after it.
The day before
Deliver materials and arrange a watch.
Mark bench and pole spots so the light falls on the seats.
Work days (2–3 days)
Footing, casting, benches; set the poles.
Keep the concrete wet for 7 days (curing).
Fit the solar lights once the cement has set.
The week after
Visit at night to see the lights are on.
Put the caretaker's name on a small board.
Who does what
- Lead (1): Permission, mason, purchases, receipts. — ____________
- Mason's helpers (2): Mix sand and cement, carry water, hand things over. — ____________
- Lights (1): Test and mount the solar lights; someone who knows wiring and batteries. — ____________
- Photos and curing (1): Before and after photos; water the concrete for a week. — ____________
The day, hour by hour
- 08:00Mason and team gather; check materials.
- 08:30Dig footings and pole holes.
- 10:00Tie rods, set the casting frames.
- 11:30Pour concrete; set poles upright in cement.
- 13:30Lunch and rest.
- 14:30Bench tops and plaster.
- 16:30Cover with wet sacking; rope or bamboo round it.
- 17:00Day's photos; plan the next day and the curing rota.
What can go wrong, and what to do
- Solar lights stolen → Mount high on the pole with clamps and bolts; ask the next-door shop to watch.
- Someone sits before the concrete sets → Rope it off with a “wet cement” sign; water for 7 days.
- Light dims after a few months → Wipe the dust off the panel; use the shop warranty if any.
- Cost runs over → Finish the benches first, lights later; pledges go straight from giver to shop.
Useful numbers
- 999National emergency: police, fire, ambulance (free)
- 333Government information, services and complaints
Questions people ask
- What if they are stolen?
- Set them in concrete, mount the lights high, and ask the shop next to them to keep an eye.
- Can I join if I cannot stay the whole time?
- Yes. Say in your request which step or which hours you can do. The lead will give that step to you.